Project Summary​

Given a 6-month completion schedule, Allied Mechanical Services utilized BIM and prefabrication to start the welded process piping fabrication at the same time underground plumbing was beginning on site. Originally over budget, the project endured thirteen value engineered deductions in a project that totaled 16,439 man-hours.